For locals in the Republic of Srpska, the construction of a Mini Hydro Power Plant Bočac 2 is not just about electrical power. This project empowers their economy and provides them with an opportunity to be a part of Europe’s green energy future. This is electrical power facility where the state-of-art specific technical solutions are built in. Installed power of the MHPP Bočac 2 is 10 MVA, and designed annual production of this mini hydro power plant is approximetly 41.6 GWh.
Investor: MH EPRS, Hidroelektrane na Vrbasu
Consortium partner: Andritz Hydro
Year: 2016-2018
Location: Bočac, RS-B&H
Our scope of works:
Basic, detail, as built design.
Consulting services throughout scope of entire electrical-mechanical and hydro-mechanical phase of works.